DATE OF DELIVERYJULY 2014
BUILDING OPENING DATEOCTOBER 2014
CONSTRUCTION SITE100.000 m²
GROSS FLOOR AREA930 - 1096 m²
NET FLOOR AREA631 - 800 m²
HEATING - COOLING SYSTEMHeating with natural gas-fired boiler, central cooling system will be made in the system with water-cooled chillers . Office ( supply of fan coils and all kinds of mechanicalinstallation works of the customer / tenant belongs ) and office corridors heating and cooling systems using 4 -pipe fan - coiler will be held. Heating and cooling costs for each individual department will be measured by calorimetry.
NO. OF LIFTS8 PASSENGERS + 1 LOAD + 3 CAR PARKS
NO. OF CLOSED CAR PARKS1012
NO. OF CAR PARKS PER FLOOR15 -18
ENVIRONMENTAL AWARENESSGOLD LEED CERTIFICATE
CONSTRUCTIONGeneral Construction: All materials used in the application works with Turkish Standards, relevant specifications and related areas of Public Works shall be in accordance with national norms.
FRONT SPIECECurtain wall system will be applied in exterior. Exterior has a high thermal and sound insulation properties.
WALLGas concrete or gypsum walls dividing wall between independent sections. Concrete or drywall gas in the tank wall. Aerated concrete and gypsum walls in the public areas will be used. Glass partition walls between offices with floor halls will be used.
WALL COATINGSGround of independent parts, the concrete surface will be released as appropriate jeans to the raised floor. Raised floor property will be made by the owner or tenant. Suitable materials for use in architectural projects in the shared social space ( natural stone , carpet, ceramic , wood, etc . ) will be used. Surface hardener and dust inhibitor in the underground parking and storage areas will be implemented.
WALL COATINGSIn the independent section of the wall made of aerated concrete or plaster over drywall will be delivered . All elevator halls of PVB glass paneling , decorative paint to be used under the plaster or concrete . Common architecture in the social area in the project in accordance with the wood, natural stone, plaster painting, etc. PVB glazing. material will be used . All services and concrete paint will be applied via the fire escape corridor.
DOORSIndependent entrance section will be done by the landlord or tenant. In areas where fire regulations require fire-resistant, certified, panic push bar steel doors will be installed. 4 entrance of the tower ( 2 rear inputs, 2 front entrance ) revolving glass door will be found.
CEILSDrywall ceilings in warehouses,depending on the projects in the areas will be delivered. Concrete ceilings, aluminum grille ceilings, wooden panel ceiling, metal ceiling will be produced . All wet areas of common use moisture resistant plasterboard ceiling will be made. Parking ceilings and concrete ceilings service corridors surface will be delivered.
WET AREASAppropriate water-saving fixtures will be used to LEED criteria 1. Quality. Aerated chamber walls in wet areas, WC cabins will be produced as an intermediate compartment and the door to the cubicle. Excluding wet areas on the ground floor of all the towers in the wet ground floors ,1st class ceramic tiles will be made according to the project.